Skip to content

Inspections reference

The complete list of fields, values, and settings of the Inspections module.

Menu item What the page shows
Schedules Inspection schedules
Defects Defects found by inspections
Journal All inspections; the To do tab shows what is due
Templates The company’s inspection templates
Library Ready-made templates to copy

The Inspection Settings page is under Settings.

Field Required Description
Name yes Template name
Asset type no If set, only assets of this type are inspected with the template. Empty means “Any asset type”
Description no What the template is for
Active — An inactive template isn’t offered for new inspections and schedules
Checklist yes Sections and items
Field Description
Item What to check
Type Answer type, see the table below
If it fails Defect severity if the item fails
Required The inspection can’t be submitted without an answer
Instructions A note shown under the item during the inspection
Type Answer When the item fails Condition
Pass / fail Pass or Fail The answer is “Fail” yes
Yes / no Yes or No The answer is “No” yes
Number A number; Min, Max, and Unit can be set The value is out of range —
Text Free text Never —
Choice One of the Choices The selected choice is marked Fails the item yes
Rating From 1 to the Number of stars (3–10) The rating is at or below Fails at or below yes
Photo One or more photos Never —
Meter reading A reading of an asset meter: running hours, mileage, or cycles Never —
Signature A handwritten signature Never —

When the inspection is submitted, a meter reading is written to the asset’s meter of the same type and can’t be lower than the current reading. If the asset has no such meter, the reading is kept only in the inspection. Inspection photos also appear in the asset’s gallery.

Severity Effect on the result
Minor Result “Passed with defects”
Major Result “Failed”
Critical Result “Failed”; an open critical defect can block checking out the asset
Result When
Passed No item failed
Passed with defects Only items with Minor severity failed
Failed At least one item with Major or Critical severity failed
Status Description
Draft The inspection has been started and answers can be changed. It has no number yet
Submitted The inspection is saved in UNIO24 and has a number and a result. It can only be changed by a correction with a reason
Status Description
Open The defect needs follow-up
Fixed The problem has been fixed: by hand, during the next inspection, or when the linked ticket or work order is done
Waived The defect won’t be fixed: by hand, when the linked ticket or work order is cancelled, or when the asset is written off

If the same item fails again while its defect is open, no new defect is created: the defect gets the line “Repeat failures: N, last on …”.

Set separately for each severity on the Inspection settings page.

Value What happens when the inspection is submitted
Nothing The defect is only recorded. This is the default
Ticket A ticket “Inspection issue: ()” is created; its requester is the person who performed the inspection
Work order A work order with the same title “Inspection issue: ()” is created
Field Description
Template Which template the inspections use
Applies to Every asset of a type or One asset
By time, Every Interval: a number and a unit (day, week, month, year)
By meter A meter and a step, for example every 250 running hours
Remind this many days ahead How many days before the due date the status becomes “Due” and the reminder is sent; no larger than the interval
Responsible A user or group who gets the reminders. Empty means everyone who can perform inspections
Active An inactive schedule creates no due dates or reminders

At least one condition, by time or by meter, has to be set.

On the asset card and in schedules On the To do tab When
Upcoming Soon The due date hasn’t come yet
Due Due The date (counting the reminder days) has arrived, or the meter has reached the threshold
Overdue Overdue The due date has passed

Only dates can be overdue: reaching a meter threshold gives the “Due” status. The To do tab shows overdue inspections, those due now, and those due within the next 14 days.

Field Values Default
Open critical defect at checkout Warn: the asset can be checked out with a warning; Block: check-out and transfers are refused until the defect is closed Warn
Number prefix Up to 10 characters; empty means numbers without a prefix INS
What a defect opens: Minor / Major / Critical Nothing · Ticket · Work order Nothing

Any open defect on an asset is shown as a warning at check-out and when the asset is moved between locations, whatever this setting says.

Field Description
Asset type The type the rule applies to. Empty means “All asset types” that don’t have a rule of their own
Check-out: template and mode Which template is filled in at check-out
Check-in: template and mode Which template is filled in at check-in
Mode Description
Off No inspection is asked for
Optional An inspection is offered, but the form can be saved without it
Required The form can’t be saved without a completed inspection

An inspection counts if it uses the rule’s template on this asset, was submitted no more than 24 hours earlier, and hasn’t been used anywhere else. The inspection result doesn’t stop a check-out; only the Block setting for an open critical defect does.

Work order form field Description
Inspections before the work Templates to check the asset with before work starts; the work order can’t be taken into work until they are completed
Inspections after the work Templates to check it with after the work; the work order can’t be finished until they are completed

States of an inspection in the Inspections block of the work order card: Not started, Started, Completed, Template turned off.

What Limit
Items per template 200
Sections per template 100
Nesting of sections and conditions 3 levels
Conditions per item 20
Choices per Choice item 100
Records of a repeatable section in one inspection 50
Templates per work order stage 20
Event in the notification settings Who gets it
Inspection failed Users with the Correct inspections and waive defects permission; if there is a critical defect, the email goes out right away
Inspection due The person responsible for the schedule; if there is none, everyone who can perform inspections
Inspection overdue The same; the overdue reminder repeats once a week

You can add the Inspections due widget to the dashboard: it shows how many assets are waiting for an inspection and how many of them are overdue.

In the role editor, the permissions are in the Inspections group.

Permission What it allows
View See the journal, inspection cards, defects, templates, schedules and the library, and the Inspections tab on the asset card
Perform inspections Start, fill in, and submit inspections; close defects as fixed
Manage inspection templates Create, edit, and delete templates and schedules, copy templates from the library, change the inspection settings and the check-out and check-in rules
Correct inspections and waive defects Correct submitted inspections with a reason, waive defects

Work order inspections can be run by anyone who is allowed to edit the work order, and check-out and check-in inspections by whoever processes the check-out or check-in. No inspection permissions are needed for that.